Skip to content

Execution 1 - Tracking, Status Reports and Change

Google Project Management Certificate · Course 4: Project Execution - Running the Project


Three courses of preparation are now behind us. The goal is set, the scope agreed, the stakeholders mapped, the charter signed, and the plan broken down into milestones, tasks, a schedule and a budget. Execution is where all of that stops being a document and becomes work people are actually doing.

The job changes shape here. In initiation and planning the project manager was mostly deciding things; in execution the project manager is mostly watching, reporting and unblocking. The question is no longer what should we do, but rather: where is this project right now compared with where the plan said it would be, and what do I do about the gap?

That question is the spine of the module. It runs from tracking progress, to reporting it honestly, to handling the risks that have stopped being hypothetical and the changes that follow. The two practical activities are writing a project status report and running a ROAM analysis on live risks.


Execution is where planning pays off, but it is not passive. The instructor frames the phase around a set of running responsibilities: track and measure progress, manage quality and continuous improvement, handle risks that actually materialise, absorb changes and scope creep, use data to make and explain decisions, lead and influence the team, communicate and run meetings, and finally close the project properly. Planning covered risk mitigation in the hypothetical; execution asks what to do when a risk stops being hypothetical and becomes today’s problem.


A deviation is anything that alters the original course of action, and it cuts both ways: finishing early because a technical problem turned out simpler than estimated is a deviation, and so is a natural disaster shutting down the testing team. Either way the project manager needs the real state of things, not the planned one.

Tracking gives youWhy that matters
TransparencyInformation is centralised so everyone sees the status of each part. Even strong project managers decide badly without context
Nothing forgottenProjects carry an enormous number of small details, and tracking stops them slipping
Shared deadlines and goalsTeam and stakeholders stay in touch with what is due when, from one plan that works for you and for them
Early risk detectionIssues surface in time for corrective action, and attention points at the areas genuinely at risk
ConfidenceA current picture that the project will land on time, in scope and on budget keeps the team motivated

The project schedule - the tasks and activities driving the completion dateStatus of action items and key tasks - is the work actually getting doneProgress toward milestonesCosts - so you neither overspend nor underspendKey decisions, changes, dependencies and risks, including agreed scope changes

New tasks appear constantly once a project is underway, which is why tasks must be tracked as they progress rather than reviewed at the milestone. And even when you do not own the whole budget, you almost certainly own tasks and resources with budget implications, so costs stay on the list.


Every project plan carries at least one tracking method, often more than one. The test is practical: choose something the whole team can understand, reference and keep up to date.

Gantt charttasks against time
Roadmapbig milestones over time
Burndown chartwork remaining against time
Three common methods, from schedule-level detail to a granular task countdown.

The most common method of all. It measures tasks against time and also carries who owns each task and what order the tasks come in. Each task is a horizontal bar whose length reflects the time allotted; bars stack so the one above must finish before the one below can. Tracked sequentially the shape falls away like a waterfall, which is why Gantt charts belong to Waterfall project management. They live in the project plan and are updated as work progresses. Best for projects with many dependencies, tasks and milestones, for staying on schedule, and for large teams, because ownership is laid out visually.

A roadmap tracks big milestones and shows a team or key stakeholders how the project should evolve over time.

Goalse.g. lift online B2C sales 20 percent year over year
Approachthe main tactics the team will use
High-level overviewthree or four sentences of objectives and priorities
Quarterly tablekey milestones per quarter, then tasks per team
A roadmap reads top down: why, how, a concise summary, then the quarter-by-quarter map.

A quarter is a three-month period on the company’s financial calendar. Most tasks map to a milestone due in the same quarter, but not all: some must finish early to unblock another team or a later milestone. In the worked example, product and engineering work through Q1 and Q2 so the refreshed online store can launch in Q3, while marketing and sales handle product testing and offering suggestions against the Q1 milestone of finalising holiday inventory. So the roadmap tracks both individual and project progress toward milestones.

The most granular of the three, measuring time against work done and work remaining. The vertical axis is the number of tasks left, the horizontal axis is time, a dotted line shows expected progress based on the rate the team should close tasks, and a solid line shows actual progress. Tracking starts in the upper left and works down toward zero tasks and right toward the end date.

Its two jobs are keeping the team on top of targeted completion dates and making scope creep visible as it happens. Typically used by Agile Scrum teams, it must be displayed where everyone can see it and updated regularly. Beyond the current project it reveals how the team really works and what affects its ability to finish on time, which makes the next project easier to plan.

If you need to…Use
Communicate milestones to a large team, or show stakeholders how the project evolvesRoadmap
Run a project with multiple dependencies and many ownersGantt chart
Track tasks tightly against a deadline, or catch scope creepBurndown chart

ComponentWhat it does
Project nameSpecific enough that the goal is understood at a glance
DateReports go out weekly or monthly depending on stakeholder needs and project pace; the date is a reference point and builds a history log
SummaryGoals, schedule, highlights and lowlights in one place, usually grouped with the timeline summary and overall status
StatusActual progress versus planned progress, commonly shown as RAG
Milestones and tasksCondensed into key accomplishments (what has happened) and upcoming (the next big milestones), rather than the item-by-item not started / in progress / completed of the project plan
IssuesCurrent roadblocks and potential risks

The issues section is where expectations get set. If the status is red or amber, say what is stopping you being where you planned to be, state the plan to get back to green, and ask for the resources or help you need to do it.

StatusMeaning
RedIssues need resolution; the project may be delayed or go significantly over budget
Amber / YellowPotential schedule or budget issues, but likely resolvable with corrective action
GreenSchedule and budget are fine, the project is on track

RAG can label the overall project status as well as individual milestone status.

Format follows audience. A complex project with many moving parts, reported to the team, is best as a spreadsheet; updates aimed at senior stakeholders are best as a slideshow carrying only the key points. Either way, status reports earn their place because they simplify communication across the team, keep stakeholders informed, give you a natural moment to request more resources or support, and record the status centrally.

A gen-AI assistant can speed up routine reporting, such as a status update for a company newsletter on a packaging machine still in testing. The framework is TCREI - Thoughtfully Create Really Excellent Inputs:

StepWhat you add
TaskWhat you want, with a persona and a format preference. Starting deliberately thin shows you what is missing
ContextTarget audience (technical or non-technical), level of detail, and tone (informative, cautionary, empowering)
ReferencesAn example, such as a previous status update that landed well, to steer the output
EvaluateIs it accurate and unbiased? The right length? The right tone? Any jargon outsiders would trip over?
IterateSet a word limit, ask for bullets, require keywords, request placeholders for images, then repeat

A risk is a potential event that might occur and could affect the project - hypothetical by definition, which is why planning identifies and prepares for it. When a risk actually occurs, the consequence is a change.

A change is any variance from the plan against the triple constraint: priorities and scope, budget and resources, or the timeline. Measure it against the baseline estimates set from the original requirements, and expect knock-on effects when you move any one of them.

Using the running bathroom remodel example:

Type of changeExample
New or changing dependenciesThe new sink cannot go in until the vanity and plumbing are in place
Changing prioritiesThe client’s in-laws move in, so the spare bedroom jumps ahead of the bathroom
Capacity and people availableThe plumber has to be replaced after problems on site
New budget or resource limitsElectrical quotes come in high, so design costs must drop by 10 percent
Scope creepThe clients love the new tile and now want every bathroom retiled
Force majeureAn unforeseen crisis stops someone fulfilling a contract, such as a union strike or a pandemic halting production. Uncommon, but real

The cautionary example is worth keeping: you budget to lift the carpet and refinish the hardwood beneath, then find the floors rotting. They need replacing, and both timeline and budget take the hit.

Managing changing scope is the project manager’s responsibility, though rarely alone. Start from the Statement of Work and the RACI chart, then use whatever change request process the team or organisation has, creating one if it does not exist. Because people in many roles fill these forms in, a change request form must be self-explanatory and thorough. The template used here is a two-column, ten-row table covering:

BlockFields
HeaderProject name; discussion owner, the person leading it from the team; discussion type, so the audience knows whether this is a risk, an opportunity or something else; teams involved
Timing and stakesTarget date for the discussion; which milestones or goals are impacted
Expected outcomeA change in priorities, a schedule change, or an official call on how to proceed
DescriptionThe current situation, the change, and the difference from the plan of record - a before and after snapshot
ProposalThe in-depth proposal for the necessary changes, addressing trade-offs
BackgroundShared context so everyone starts from the same understanding

Think of a line of dominoes: knock one over and it takes the next with it. A construction firm must name a foreman and a project manager before requirements, timeline and budget are signed off and the crew is picked - you would never put a crew to work before the job is scoped and the contracts signed.

TypeWhat it meansExample
InternalA relationship between two tasks in the same projectForeman and PM chosen, then requirements signed off, then crew selected
ExternalTasks reliant on outside factors such as regulators or other projectsDemolition waits on city approval. Often outside your control, but must stay visible
MandatoryLegally or contractually requiredPour the foundation, then have the city inspect it before building continues
DiscretionaryDefined by the team - things that could happen independently but were deliberately linkedPour a test portion using a new supplier’s concrete to estimate the total needed
  1. Proper identification. Brainstorm every possible dependency with the team and categorise them.

  2. Recording. Build a risk register, a table or chart listing risks and dependencies. For each dependency record a description, the date, and every activity or task it could affect.

  3. Continuous monitoring and control. Schedule regular check-ins on the interrelated tasks, stay current on progress, and watch for changes that will hit other tasks.

  4. Efficient communication. Keep the team and stakeholders updated, since that is what actually resolves dependencies and keeps momentum.

Defining dependencies clearly at the project outset, as in the foundation example, is what makes this manageable later.


The highest-leverage move is indirect: manage changes and dependencies and manage scope creep, and most other risks become easier. Dependencies met on time keep the team on schedule; a tightly managed scope keeps the budget intact and the timeline from stretching.

Brainstorming with the team is the most effective way to find risks, because teammates bring experience from earlier projects and spot repeats of old problems. Ask what could improve the outcome and what could hurt or hinder it, then record each one in the risk register as an if / then statement: if this event happens, then this is the impact.

To prioritise, calculate risk exposure - a way to measure the potential future loss from a specific activity or event. Build a matrix on two variables: risk impact across the top horizontal axis and probability down the side vertical axis, each marked high, medium and low. Plot every risk at the intersection of the two, and the ones needing immediate attention become obvious.

No register catches everything, so unforeseen risks always arrive. ROAM is the technique for deciding what to do with a risk after it has materialised - it manages actions, not predictions.

Resolved done with it
  • The risk has been eliminated and will not be a problem
Owned assigned
  • A team member is given ownership, entrusted to handle it, and monitored through to completion
Accepted live with it
  • It has been agreed that nothing will be done about it
Mitigated reduced
  • Action has been taken that lowers either the likelihood or the impact
Sort every live risk into one of the four, then discuss the sorted set as a team and decide which risks take priority.

The Paw Snacks puppy treat launch shows the chain working. Six weeks before launch the bakery tells the project manager, Naja, that the bone-shaped cookie cutters have not arrived, and baking must start the next day. Her teammate Abe finds the order delayed by a product shortage and now landing two days late. The launch cannot move, because marketing has already bought non-refundable advertising for launch day.

The save came from work done months earlier: the team had brainstormed risks, built a risk register with a probability and impact matrix, rated a cookie cutter delay as medium probability and high impact, and had Abe write a mitigation plan approved by the sponsor and stakeholders. It offered two options - raise the bakery’s daily output to recover the lost days, or bring in a second bakery - and they chose the first to avoid onboarding another supplier. Then came the step that is easy to skip: they brainstormed the risks of the new plan, judged that a slightly smaller order would only dent projected growth, decided to accept that risk rather than delay further, and took it to the sponsor for approval before acting.

TermMeaning
Mitigation planA planned risk response strategy, written early for known risks that threaten schedule, cost or scope
Contingency planMostly funds held outside the planned budget, to support a risk response that runs over or to cover unforeseen risks during execution

Escalation sounds negative, but in project management it should be encouraged, used often and even celebrated. It is a checks and balances mechanism, it produces fast decisions, and an objective third party can settle what two teammates cannot. It also encourages participation, since inviting others to solve or own a problem builds trust and shared responsibility.

Set escalation standards before work begins, agreed between the project manager, the team and the sponsor: who issues are raised to, how they are raised, and the forum for the discussion. Then escalate at the first sign of a critical problem - anything hitting the triple constraint of time, budget and scope.

A delay to a major project milestoneBudget overrunsAnything that could lose a customerAnything pushing back the estimated completion date

Escalation exists to head off two specific failures:

ProblemWhat it looks like
Trench warsTwo peers or groups cannot agree and neither will give ground, so the project stalls and progress slips
Bad compromisesBoth sides settle on a so-called solution but the end product still suffers. Compromise while keeping the larger project goals in view, and be ready to help people make a hard choice for the greater good
PracticeHow it reads
Keep a friendly toneThe instinct under pressure is to get straight to the point, but you are asking for help. Open with goodwill, describe the issue without blame, close by thanking them
State your connection to the projectOne sentence with your name, role and relationship to the project, so the reader knows why you are writing
Explain the problemState clearly what needs solving, with enough context and no more. Dense paragraphs invite skimming
Explain the consequencesBe specific about how it is hurting the project now, or will hurt it later in the timeline
Propose a course of action and make a requestThe central piece: offer a solution and say exactly what you need from the recipient

In the worked example, a project manager whose supplier delivered 3,000 of 5,000 candles, many damaged, names the risk to customer satisfaction, quantifies the consequence as a three-week launch delay plus 20,000 dollars of extra cost, then proposes two vetted backup suppliers and asks for a meeting the next day. Brief, blameless, impossible to misread.


Even small changes matter to someone, and all of them should be communicated. Tailor the channel to the subject and the recipient.

SituationChannel
A small change affecting one personEmail. Give a heads up and set a meeting time; avoid emotional topics or anything needing depth
A big change affecting more than one person, likely to move budget, deadline or scopeA team meeting
Something needing quick agreement, or slightly sensitiveThe instructor’s own habit: a quick coffee or hallway chat, then an email recording what was agreed

Weekly meetings are not compulsory. If the agenda is thin, cancel and pivot to email, or move the topic to another forum.



Next: Quality Management → - making sure what ships is actually right.