One live view of every case before the Supreme Court, High Courts, CAT and the appellate forums: what is pending, what was decided, what was appealed, which counters are due and which hearings are coming up.
Power BIData integrationData modellingKPI designLegal operationsManagement reporting
Built during: my legal posting in India’s indirect-tax administration, as the nodal officer for litigation (see experience) · My role: creator and sole project lead, working under the guidance of senior authorities · Built with: Power BI and Excel · The name:Sankalan means “compilation” in Hindi.
4+types of forum: Supreme Court, High Courts, CAT and appellate forums
1shared template, with one sheet kept by each commissionerate
1central dashboard: the single source for litigation reporting
Livehearings, counters, appeals and disposals, as each unit updates
Cases ran in many forums at once: the Supreme Court, the High Courts, the Central Administrative Tribunal (CAT) and the appellate tribunals and authorities. Each commissionerate kept its own records in its own format, so a simple question from senior authorities, such as how many cases were pending in the High Court and which came up this week, meant calling every unit and compiling the answers by hand.
What I built
A central litigation dashboard in Power BI, connected to an Excel sheet kept by each commissionerate in one shared format. It showed, live, how many cases were pending, disposed, appealed or awaiting a counter, and which hearings were coming up, from the zone total down to a single case.
My role
As the nodal officer for litigation, I held the records for every forum. I created the dashboard and was the sole project lead, working under the guidance of senior authorities: I designed the shared template, connected and cleaned the sheets, built the data model and measures, designed the report pages, and used it to report to senior authorities.
The result
One central, trusted place for the status of every case. Reporting to senior authorities no longer meant a fresh round of compilation, and hearings, pending counters and appeal decisions became visible early enough to act on.
I ran Sankalan as a project from start to finish: I proposed it, got it approved, gathered the requirements from the people who would use it, built it, piloted it, rolled it out to every commissionerate, trained the officers who kept the sheets, reported progress upwards, and handed it over to my successor when my posting ended.
Initiate2022 · proposal and approval
→
Plan2022 · requirements from users
→
Build and test2022 · template, model, reports
→
Pilot2022 · first units, fixes
→
Roll out and trainevery commissionerate
→
Monitor2022-2023 · follow-up, reporting
→
Close2023 · handover to my successor
The full life cycle, owned end to end, under the guidance of senior authorities.
Owner
As nodal officer for litigation, I was the single owner of the project: the idea, the plan, the build, the rollout and the results.
Sponsor and approval
Senior authorities approved the proposal, received the progress reports and used the dashboard; I worked under their guidance throughout.
Users and stakeholders
The legal sections of every commissionerate, who kept the sheets, and the senior authorities and review meetings that relied on the figures.
Decisions I owned
What to capture and how, the template and its dropdowns, the data model and report pages, the pilot, the rollout and the update routine.
Phase
What I did
Output
Initiate
Saw that every request from senior authorities set off a new round of calls and spreadsheets; proposed one shared case register and a central dashboard; obtained approval
Approved proposal
Plan
Talked to the officers who kept the case records and to those who asked for the reports, to learn what they tracked and what they needed; fixed the scope (forums, case stages, deadlines) and the template fields; planned a pilot before the full rollout
Agreed fields and report list, pilot plan
Build and test
Built the Excel template with dropdowns, the Power Query connections, the data model, the measures and the report pages, and tested them with real records
Working template and dashboard
Pilot
Ran it first with a few units and fixed what confused users or broke the combine step before going wider
Refined template and dashboard
Roll out and train
Sent the template to every commissionerate, showed the officers how to fill and update it, and answered their questions in the first weeks
Every unit on one template
Monitor and control
Used the dashboard’s flags to see which units were missing updates or falling behind, followed them up, and reported progress and litigation status to senior authorities
Regular reports from one source
Close and hand over
Handed the template, the dashboard and the update routine over to the next officer when my posting ended
A running system with a new owner
The problem: time-critical information, scattered everywhere
Litigation is where small slips become expensive. A counter affidavit not filed before a hearing, or an appeal period allowed to lapse, can decide a case before its merits are ever argued. Yet the information needed to prevent that was spread across commissionerates, forums and files.
Where do we stand?
How many cases are pending, in which forum, on which subject and in which commissionerate? How long have they been pending?
What is coming up?
Which hearings are this week, and has the counter or reply been filed for each of them?
How are we doing?
How many cases were disposed, and how many in the department’s favour? Was every adverse order appealed in time, or a decision recorded not to appeal?
Why it was hard
Scattered records
Every commissionerate kept its own register, in its own layout
Many forums
Each forum has its own case types, stages and timelines
Time-critical
Hearing dates and limitation periods for appeals leave no room for late information
Repeated compilation
Every review meeting or request from senior authorities started a fresh round of calls and spreadsheets
No common view
There was no way to see which unit was behind on counters, appeals or updates
The solution: one template, one model, one dashboard
From one sheet per commissionerate to a single dashboard: combine, model, report.
One template for every commissionerate. I designed a single Excel template with fixed columns and dropdowns for forum, stage, outcome and counter status, so every unit recorded its cases the same way and the sheets could be combined without manual rework.
Ownership stays with the unit. Each commissionerate kept and updated its own sheet, because the unit handling a case knows it best. The dashboard only read the sheets; it never changed them.
One central connection. Power BI connected to all the sheets through Power Query, appended them into one case table, cleaned dates and names, and flagged records with missing fields or sheets that had not been updated recently.
A model built around the case. Cases were linked to forums, commissionerates and a date table, with measures for pending and disposed cases, outcomes, appeal decisions, counters due and overdue, and the days left to each hearing and each appeal deadline.
Report pages for each question. An overview for senior authorities, a hearings-and-deadlines page for what needed action, a side-by-side view of the commissionerates, and a case register that any total could be filtered down to.
Reporting upwards. As the nodal officer, I used the dashboard to report to senior authorities: figures for review meetings, answers to questions as they came, and periodic reports, all from the same source.
Four report pages, each answering one question. The reconstructions below show three of them, with their layout and the kind of measures on each, using invented figures.